Bid Tabulation Results for GSP Rehabilitation of Concrete Median Barrier - Milepost 134 to 140
Dear New Jersey Turnpike Authority
This is a request for public records made under OPRA and the common law right of access. Please acknowledge receipt of this message.
Records requested:
Please send the final and compiled bid tabulation (Bid Tally), including all quantities and unit pricing for each bidder, for GSP Rehabilitation of Concrete Median Barrier - Milepost 134 to 140 that was submitted on 7/25/2023 11:00 AM.
Below is an example of the format we are looking for that the engineer usually creates at the completion of the bid:
| | BIDDER 1 | BIDDER 2 |
|-------------------------------------------------------------------------------|
| Item | Description | QNT | UNIT | AMOUNT | UNIT | AMOUNT |
| | | | | |
| | | | | |
| | | | | |
Please send all documents electronically.
Thanks,
PPA
Ms. Baisley,
Responsive to your OPRA request, the referenced contract T100.586 award is
still subject to veto, which will expire on Wednesday, August 9, 2023. The
requested bid tabulations will be provided to you the next business day,
Thursday, August 10, 2023.
Thank you
Alethea Humphreys
Law Department
New Jersey Turnpike Authority
P.O. Box 5042
Woodbridge, NJ 07095
732-750-5300 Ext. 8738
[1][email address]
-----Original Message-----
From: Maddie Baisley
<[2][OPRA #49074 email]>
Sent: Wednesday, July 26, 2023 4:18 PM
To: NJ Turnpike Authority <[3][NJTA request email]>
Subject: OPRA request - Bid Tabulation Results for GSP Rehabilitation of
Concrete Median Barrier - Milepost 134 to 140
[You don't often get email from
[4][OPRA #49074 email]. Learn why this is
important at [5]https://aka.ms/LearnAboutSenderIdentific... ]
CAUTION: This email originated from outside of the NJTA email system. Do
not click on links or open attachments unless you were expecting this
email.
Dear New Jersey Turnpike Authority
This is a request for public records made under OPRA and the common law
right of access. Please acknowledge receipt of this message.
Records requested:
Please send the final and compiled bid tabulation (Bid Tally),
including all quantities and unit pricing for each bidder, for GSP
Rehabilitation of Concrete Median Barrier - Milepost 134 to 140 that was
submitted on 7/25/2023 11:00 AM.
Please deliver records electronically via email to the below UNIQUE
address for all replies to this request:
[6][OPRA #49074 email]
References
Visible links
1. mailto:[email address]
2. mailto:[OPRA #49074 email]
3. mailto:[NJTA request email]
4. mailto:[OPRA #49074 email]
5. https://aka.ms/LearnAboutSenderIdentific...
6. mailto:[OPRA #49074 email]
Ms. Baisley,
In our previous email response dated August 8, 2023, contract T100.586 was
referenced and was incorrect. The correct contract number for your OPRA
request is P200.589.
Our office is currently processing your OPRA and requires an extension of
time. Our office will provide a response, or an update, by Friday, August
18, 2023, or sooner, if possible.
Thank you.
Alethea Humphreys
Law Department
New Jersey Turnpike Authority
P.O. Box 5042
Woodbridge, NJ 07095
732-750-5300 Ext. 8738
[1][email address]
From: Humphreys, Alethea
Sent: Tuesday, August 8, 2023 4:01 PM
To: [OPRA #49074 email]
Cc: Paxton, Jane <[email address]>; de la Cruz, Ramon <[email address]>
Subject: OPRA #9933 request - Bid Tabulation Results for GSP
Rehabilitation of Concrete Median Barrier - Milepost 134 to 140
-----Original Message-----
From: Maddie Baisley
<[2][OPRA #49074 email]>
Sent: Wednesday, July 26, 2023 4:18 PM
To: NJ Turnpike Authority <[3][NJTA request email]>
Subject: OPRA request - Bid Tabulation Results for GSP Rehabilitation of
Concrete Median Barrier - Milepost 134 to 140
[You don't often get email from
[4][OPRA #49074 email]. Learn why this is
important at [5]https://aka.ms/LearnAboutSenderIdentific... ]
CAUTION: This email originated from outside of the NJTA email system. Do
not click on links or open attachments unless you were expecting this
email.
Dear New Jersey Turnpike Authority
This is a request for public records made under OPRA and the common law
right of access. Please acknowledge receipt of this message.
Records requested:
Please send the final and compiled bid tabulation (Bid Tally),
including all quantities and unit pricing for each bidder, for GSP
Rehabilitation of Concrete Median Barrier - Milepost 134 to 140 that was
submitted on 7/25/2023 11:00 AM.
Please deliver records electronically via email to the below UNIQUE
address for all replies to this request:
[6][OPRA #49074 email]
References
Visible links
1. mailto:[email address]
2. mailto:[OPRA #49074 email]
3. mailto:[NJTA request email]
4. mailto:[OPRA #49074 email]
5. https://aka.ms/LearnAboutSenderIdentific...
6. mailto:[OPRA #49074 email]
Dear Humphreys, Alethea,
We would like to follow up on this request. We are looking for a bid tabulation with unit prices per item from each bidder with the list of items. Looking forward to receive it from you the soonest.
Yours sincerely,
Maddie Baisley
Ms. Baisley,
Responsive to your recent email and OPRA request #9933, attached is the requested bid tabulation for contract P200.589, Garden State Parkway Rehabilitation of Concrete Median Barrier- Milepost 134-140.
This completes this OPRA.
Thank you.
Alethea Humphreys
Law Department
New Jersey Turnpike Authority
P.O. Box 5042
Woodbridge, NJ 07095
732-750-5300 Ext. 8738
[email address]
-----Original Message-----
From: Maddie Baisley <[OPRA #49074 email]>
Sent: Wednesday, September 13, 2023 2:51 PM
To: Humphreys, Alethea <[email address]>
Subject: RE: OPRA #9933 request - Bid Tabulation Results for GSP Rehabilitation of Concrete Median Barrier - Milepost 134 to 140
CAUTION: This email originated from outside of the NJTA email system. Do not click on links or open attachments unless you were expecting this email.
Dear Humphreys, Alethea,
We would like to follow up on this request. We are looking for a bid tabulation with unit prices per item from each bidder with the list of items. Looking forward to receive it from you the soonest.
Yours sincerely,
Maddie Baisley
-----Original Message-----
Ms. Baisley,
In our previous email response dated August 8, 2023, contract T100.586 was
referenced and was incorrect. The correct contract number for your OPRA
request is P200.589.
Our office is currently processing your OPRA and requires an extension of
time. Our office will provide a response, or an update, by Friday, August
18, 2023, or sooner, if possible.
Thank you.
Alethea Humphreys
Law Department
New Jersey Turnpike Authority
P.O. Box 5042
Woodbridge, NJ 07095
732-750-5300 Ext. 8738
[1][email address]
From: Humphreys, Alethea
Sent: Tuesday, August 8, 2023 4:01 PM
To: [OPRA #49074 email]
Cc: Paxton, Jane <[email address]>; de la Cruz, Ramon <[email address]>
Subject: OPRA #9933 request - Bid Tabulation Results for GSP
Rehabilitation of Concrete Median Barrier - Milepost 134 to 140
-------------------------------------------------------------------
Please use this UNIQUE email address for all replies to this request and no other:
[OPRA #49074 email]