Dear Ms. Baisley,
Ms. Jackson replied to this request on Nov. 16, 2023, however looks like
the ema...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract T200.843. Please be advised, this information is also avai...
Ms. Baisley,
Responsive to your recent email and OPRA request #9933, attached is the requested bid tabulation for contract P200.589, Garden State Par...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract T100.587, Deck Reconstruction, MP 90.0 to 91.37.
This co...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract T100.564, New Jersey Turnpike Replacement of Structure No....
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract #T100.652, NJ Tpk Bridge Repairs & Resurfacing MP 0-92 Pe...
Ms. Baisley,
Responsive to your OPRA, please see the attached bid tabulation for contract P500.720, Replacement of State Police Substations & Site Imp...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract #A200.784, Guide Rail Improvements NJTPK MP 0-122 & GSP MP...
Please see attached.
Wendy Barras, R.M.C C.M.R
Township Clerk/Registrar
Township of Mansfield
100 Port Murray Rd.
Port Murray, NJ 07865...
Please see attached. Please let me know that you've received this email and attachment and if we can be of further assistance. This is email 6 of 8....
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract #T100.584.
This completes this OPRA.
Thank you.
Alethea...
Ms. Baisley,
Responsive to your OPRA, attached is the Bid Results for NJTA Deck Rehab of Newark Bay, Hudson County Extension (NB-HCE) Zones 2 & 3..
T...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract #P200.545, Culvert Repairs Milepost 112 to 113.
For your...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for Garden State Parkway Culvert Rehab MP 115.80, 115.80A,115.81, contr...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulations for NJ Turnpike Bridge Superstructure & Median Barrier Reconstruction,...
Ms. Baisley,
Our office is in receipt of the below OPRA request. Please be advised that the bid tabulations for the NJ Turnpike Roadway Resurfacing MP...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for NJ TPK Bridge Repair/Resurfacing MP 92to 122 Newark Bay Ext.
This...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract T200.570, NJ Turnpike Roadway Lighting Repairs, Interchang...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for NJTP Replacement of Structure Nos E112.95A & E112.95B.
This comple...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for contract T100.560. For future requests bid tabulation information c...
Ms. Baisley,
Our office is in receipt of the below OPRA request. Please be advised that the bid tabulations for Guide Rail Improvements NJTPK Roadway...
Link: [1]File-List
Link: [2]Edit-Time-Data
Ms. Gomez,
Responsive to your OPRA, attached is the requested MVA report.
The OPRA is now clo...
Ms. Baisley,
Responsive to your OPRA, attached is the requested bid tabulation for GSP Bridge Superstructure Repl MP 106.3 - 106.5, contract P100.590....
Link: [1]File-List
Link: [2]Edit-Time-Data
Dear Ms. Baisley:
Responsive to your OPRA submission, attached please find the requested bid
tabul...
Link: [1]File-List
Link: [2]Edit-Time-Data
Dear Ms. Baisley:
Our office in in receipt of the below OPRA request. Please clarify the
roadway...