Bid Tabulation Results for 2023 Boardwalk Rehabilitation: Phase III, IV & V
Dear Wildwood City,
This is a request for public records made under OPRA and the common law right of access. Please acknowledge receipt of this message.
Records requested:
Please send the final and compiled bid tabulation (Bid Tally), including all quantities and unit pricing for each bidder, for 2023 Boardwalk Rehabilitation: Phase III, IV & V that was submitted on 8/17/2023.
Below is an example of the format we are looking for that the engineer usually creates at the completion of the bid:
| | |
| BIDDER 1 | BIDDER 2 |
————————————————————————————————
Item | Description | QNT | UNIT | AMOUNT | UNIT | AMOUNT |
| | | | |
| | | | |
| | | | |
| | | | |
Please send all documents electronically.
Thanks,
PPA
Good Afternoon Ms. Baisley:
Attached is the document that you requested on your OPRA Request dated September 12, 2023. Please advise by email that you received this notice.
Thank you
Karen